As part of the project of raising Highway 2 above Nahal Polg and the sinking road embankment in the Netanya area, two push-over bridges were designed with an area of approximately 10,000 square meters and a length of approximately 245 m each. In order to maintain the massive flow of traffic on Highway 2, the bridges were designed In the project using the compression method. The design included a complex geometric adjustment, due to dealing with the fact that the bridge route has both a vertical and horizontal curve. In this project, supporting and acoustic walls of various types, water diverters, sign bridges, an agricultural bridge, as well as a casting yard for the bridge sections were also planned.